Cyber Monday Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: xmasmnth

A project manager is assigned to a long-term project.

A project manager is assigned to a long-term project. The project manager came across a government debate over a new law that may affect the project.

Which first two actions should the project manager perform? (Choose 2)

A.

Create a change request to discuss with the change control board (CCB).

B.

Perform a risk identification process with the project team.

C.

Ask the project sponsor for additional budget for contingency.

D.

Consult with the project stakeholders and evaluate the impact.

E.

Discuss the possible impacts with subject matter experts (SMEs).

PMI PMP Summary

  • Vendor: PMI
  • Product: PMP
  • Update on: Dec 5, 2025
  • Questions: 2040
Price: $52.5  $149.99
Buy Now PMP PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method