A project manager is assigned to a building construction project.

A project manager is assigned to a building construction project. The project manager has taken an agile course and wants to use agile practices in the project.

What should the project manager do?

A.

Hire a consultant to provide a second opinion about whether agile can be applied to a construction project.

B.

Choose the agile practices that can be implemented in this type of construction project and apply them.

C.

Review the stages of the project to allocate additional budget for agile resources.

D.

Assign a scrum master to the project to implement agile practices in the project.

PMI PMP Summary

  • Vendor: PMI
  • Product: PMP
  • Update on: Dec 5, 2025
  • Questions: 2040
Price: $52.5  $149.99
Buy Now PMP PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method