A project manager is in the process of authoring the communications management plan for a...

A project manager is in the process of authoring the communications management plan for a new project. One of the project's stakeholders has a habit of posting work updates on social media, which may include confidential project status updates.

What should the project manager do?

A.

Ensure that social media posts related to the project are removed.

B.

Ensure that sensitive information is not included in stakeholder updates.

C.

Review social media access and restrict it to ensure confidentiality.

D.

Review the protocols and security measures to ensure confidentiality.

PMI PMP Summary

  • Vendor: PMI
  • Product: PMP
  • Update on: Oct 19, 2025
  • Questions: 594
Price: $52.5  $149.99
Buy Now PMP PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method