A project manager is leading a project that is on time and under budget.

A project manager is leading a project that is on time and under budget. In the

weekly meeting with the team, the project manager finds out that one of the tasks due next

week does not have an assigned resource available for it. The resource is currently assigned

to another project.

What should the project manager do to manage the situation?

A.

Ask the procurement department to supply a different resource.

B.

Change the schedule according to the availability of the resource.

C.

Ask the sponsor to obtain the resource as originally planned.

D.

Contact the other project manager to request the resource.

PMI PMP Summary

  • Vendor: PMI
  • Product: PMP
  • Update on: Aug 13, 2025
  • Questions: 1988
Price: $52.5  $149.99
Buy Now PMP PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method