A project manager is leading a project to develop accounting software for a trading firm.

A project manager is leading a project to develop accounting software for a trading firm. As the outcomes are being delivered, a new risk is

identified regarding an indirect tax regulation that is being changed by the government in the next 6 months. This risk will have a significant impact

on the project outcomes.

What should the project manager do next?

A.

Determine the impact of the risk and prioritize outcomes that do not affect the tax module.

B.

Delay developing the indirect tax module until the tax regulation comes into effect.

C.

Assess the impact of the risk with an expert and prioritize further outcomes with the client.

D.

Analyze the impact of the risk and discuss with the team to determine how to separate the tax module.

PMI PMP Summary

  • Vendor: PMI
  • Product: PMP
  • Update on: Dec 5, 2025
  • Questions: 2040
Price: $52.5  $149.99
Buy Now PMP PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method