A project manager is leading a software development project.

A project manager is leading a software development project. At the start of the project, the project team decides that iterations are the best way to run the project and deliver value to the customer more quickly.

Which three actions should the project manager take? (Choose 3)

A.

Develop the project management plan based on the requirements requested by the customer.

B.

Develop the application as requested by the customer, based on the approved project requirements.

C.

Plan a minimum viable product (MVP) to get early feedback from the customer.

D.

Facilitate a focus group to assess the functionality before development.

E.

Use an agile approach to deliver the product based on sprints.

PMI PMP Summary

  • Vendor: PMI
  • Product: PMP
  • Update on: Dec 5, 2025
  • Questions: 2040
Price: $52.5  $149.99
Buy Now PMP PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method