A project manager is managing the opening of a new office overseas.

A project manager is managing the opening of a new office overseas. At the beginning of the project, possible delays due to legal permits are raised by one stakeholder. Subject matter experts (SMEs)

reassessed the concern and suggested assigning more time for this permit, and the change control board (CCB) agrees.

Which document should the project manager update first to document this change?

A.

Scope baseline

B.

Cost baseline

C.

Risk register

D.

Schedule baseline

PMI PMP Summary

  • Vendor: PMI
  • Product: PMP
  • Update on: Aug 13, 2025
  • Questions: 1988
Price: $52.5  $149.99
Buy Now PMP PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method