A project manager is overseeing a 10-mile piping installation project that was supposed to spend...

A project manager is overseeing a 10-mile piping installation project that was supposed to spend US$15,000 per mile of piping installation and should complete the project exactly 20 weeks from its start. The project manager just found out that only 80% of the work has been completed.

What is the budget at completion (BAC)?

A.

US$100,000

B.

US$150,000

C.

US$300,000

D.

US$250,000