A project manager is working on a software development project.

A project manager is working on a software development project. The project manager and the project team identified the project risks. As the

project progressed, one of the risks materialized, and the project manager referred to the risk management plan to determine how to manage the risk. Once the risk management strategy was chosen and implemented, the risk was closed.

At what point did the project manager move the risk from the risk register to the issue log?

A.

Risk monitored

B.

Risk occurred

C.

Risk managed

D.

Risk identified

PMI PMP Summary

  • Vendor: PMI
  • Product: PMP
  • Update on: Aug 13, 2025
  • Questions: 1988
Price: $52.5  $149.99
Buy Now PMP PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method