PMI PMP Question Answer
A project manager is working on a project that has strict deadlines and budget restrictions. The project manager realizes that in order to win the bid the company submitted a significantly tower bid than their local competitors leaving a thin profit margin. The client is constantly submitting change requests and. unfortunately, these change requests are stretching both the schedule and the budget
What should the project manager do?
PMI PMP Summary
- Vendor: PMI
- Product: PMP
- Update on: Aug 13, 2025