PMI PMP Question Answer
A project manager is working on a software development project. Software development will be carried out through a partnership with a vendor based on a list of initial requirements not yet completely defined.
What type of contract and project approach should the project manager consider?
PMI PMP Summary
- Vendor: PMI
- Product: PMP
- Update on: Dec 5, 2025
- Questions: 2040

