PMI PMP Question Answer
A project manager leads a software development project in a hybrid environment. During project planning, the project manager identified a risk where a technical resource for a critical path item may not be available when needed. One week before the resource is needed, the technical engineer had a personal emergency and had to take a leave.
What should the project manager do next?
PMI PMP Summary
- Vendor: PMI
- Product: PMP
- Update on: Dec 5, 2025
- Questions: 2040

