A project manager of a software company is working with a cross-functional team to deliver...

A project manager of a software company is working with a cross-functional team to deliver a product to an important client. While preparing the backlog items, it

becomes clear that the responsibility for an important component lies with another product division. This division has not been involved in the project concept phase.

What should the project manager do?

A.

Ask the resource manager to assign software developers from the other division.

B.

Involve the other division ' s product owner in comparing the resource needs and product roadmap.

C.

Inform the client that the project might be delayed because of resource and planning issues.

D.

Ask the project team to come up with an alternative feature that can replace the component in question.

PMI PMP Summary

  • Vendor: PMI
  • Product: PMP
  • Update on: Aug 2, 2026
  • Questions: 187
Price: $52.5  $149.99
Buy Now PMP PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method