A project manager receives information in preparation for reporting the project's monthly performance to the project steering committee,

* Actual progress = 2 units

* Planned progress = 3 units

* Actual cost (AC) = 2 units

* Budgeted cost = 3 units

What statement should the project manager make to the project steering committee?

A.

The project is currently behind schedule with a corresponding lower cost, and every effort is being made to expedite the delayed activities.

B.

The project is currently behind schedule with a corresponding cost savings, and no further actions should be taken.

C.

The project is currently behind schedule but at a lower cost, and an application for a time and budget extension will be submitted.

D.

The project is currently behind schedule but is under the planned expenditure, and the project manager is pleased to declare a project cost savings,

PMI PMP Summary

  • Vendor: PMI
  • Product: PMP
  • Update on: Aug 13, 2025
  • Questions: 1988
Price: $52.5  $149.99
Buy Now PMP PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method