A project manager submits a version of the software that the project team created.

A project manager submits a version of the software that the project team created. During the review meeting, a team member informs the project manager of a recent regulation that requires a dual verification process in the software. However, the product sponsor strongly insists there should be no updates to the software.

What should the project manager do?

A.

Include the new requirement in the next iteration of the software without informing the sponsor.

B.

Inform the team that the sponsor decided to reject any changes and release the software as is.

C.

Release the software as is and start a new project to deliver the new requirements.

D.

Collect the requirements of the regulation and follow the change control process.

PMI PMP Summary

  • Vendor: PMI
  • Product: PMP
  • Update on: Aug 13, 2025
  • Questions: 1988
Price: $52.5  $149.99
Buy Now PMP PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method