A project manager submits several requests to purchase required hardware andknows from previous experience that...

A project manager submits several requests to purchase required hardware and

knows from previous experience that this kind of procurement usually results in disputes

between the company and its suppliers. How can the project manager mitigate this risk in the

request for proposal (RFP) with suppliers?

A.

Ask the legal team to review the RFP.

B.

Ask the project team to submit the RFP.

C.

Request approval of the RFP from the project sponsor.

D.

Request approval of the RFP from management.

PMI PMP Summary

  • Vendor: PMI
  • Product: PMP
  • Update on: Aug 13, 2025
  • Questions: 1988
Price: $52.5  $149.99
Buy Now PMP PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method