A project sponsor asks the project team to add an enhancement to the project How...

A project sponsor asks the project team to add an enhancement to the project How should the project manager address this request?

A.

Check if the budget can cover the enhancement

B.

Accept the request because it came from the project sponsor

C.

Refuse the project sponsor's request because it is out of scope

D.

Validate the proposed change's impact on the project.