PMI PMP Question Answer
A project team is working on the design of a solution for a complex project. Due to a lack of clarity of the customer's requirements, daily meetings
were agreed upon between the team and the customer. There are a few external contractors in the project who do not agree with this idea as they
feel it is a waste of time.
What should the project manager do?