A project team member raised a risk that the threat of country-wide power cuts may...

A project team member raised a risk that the threat of country-wide power cuts may affect the project time line for a software development project. In the last month, this risk

materialized and the project time line had to be extended by 2 months.

Which two actions should the project manager take? (Choose two)

A.

Ask the team member to work overtime to make up the time lost so that the project schedule is not impacted.

B.

Analyze the impact of the issue and submit a change request to update the project schedule.

C.

Inform the project sponsor that the risk has materialized and request that the project budget be increased.

D.

Extend the project deadline and update the project schedule to reflect the delay.

E.

Log it in the risk register and work with the relevant owner to implement the mitigation action plan.

PMI PMP Summary

  • Vendor: PMI
  • Product: PMP
  • Update on: Aug 13, 2025
  • Questions: 1988
Price: $52.5  $149.99
Buy Now PMP PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method