A supplier that the company has used for years has trouble accepting the new terms...

A supplier that the company has used for years has trouble accepting the new terms of an agile contract. They do not understand the terms in the contract and feel they should not have to sign it because they have had a long relationship with the company.

Which action should the project manager take?

A.

Ask the team if they can do the work until there is an available supplier.

B.

Train the supplier in agile approaches to help them understand the contract.

C.

Issue a request for proposal (RFP) to find new suppliers with agile experience.

D.

Change contract terms and conditions to avoid losing the supplier.

PMI PMP Summary

  • Vendor: PMI
  • Product: PMP
  • Update on: Oct 19, 2025
  • Questions: 594
Price: $52.5  $149.99
Buy Now PMP PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method