A team has been working together for several months and has successfullydelivered work.

A team has been working together for several months and has successfully

delivered work. A new team member has joined the team but is having difficulty

contributing.

What should the project manager do to help the new team member integrate effectively?

A.

Give the new team member time to contribute until they ask for help and support.

B.

Assign the new team member tasks so that the team member knows on what to focus.

C.

Approach the team member to identify any issues and then plan a resolution accordingly.

D.

Review the project with the team member to ensure the project scope is understood

PMI PMP Summary

  • Vendor: PMI
  • Product: PMP
  • Update on: Aug 13, 2025
  • Questions: 1988
Price: $52.5  $149.99
Buy Now PMP PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method