A team is delivering features to a customer at every iteration.

A team is delivering features to a customer at every iteration. After completing each iteration, the customer is invited for a review. However, the customer is frequently not

available and the review is often delayed, which results in increased rework for the team.

What should the project manager do?

A.

Ask the customer to review the deliverables in each iteration based on their availability.

B.

Request the customer to clarify all requirements at the start of each iteration.

C.

Plan ahead and define the best way to review the deliverables with the customer.

D.

Include the customer in daily project activities to gain the required guidance.

PMI PMP Summary

  • Vendor: PMI
  • Product: PMP
  • Update on: Aug 13, 2025
  • Questions: 1988
Price: $52.5  $149.99
Buy Now PMP PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method