A team member mentions to the scrum master that the user stories are too long.

A team member mentions to the scrum master that the user stories are too long. The team member believes this may be the cause of the team's inability to deliver value for stakeholders.

What should the scrum master do?

A.

Review the user stories with the team and ask the product owner to break them down into more manageable units.

B.

Review the user stories with the stakeholders and ask the product owner to break them down into more manageable units.

C.

Ask the team member to suggest using shorter user stories to the product owner so that the next sprint can move faster.

D.

Ask all the team members for their views about using shorter user stories so that value can be created for stakeholders.

PMI PMP Summary

  • Vendor: PMI
  • Product: PMP
  • Update on: Aug 13, 2025
  • Questions: 1988
Price: $52.5  $149.99
Buy Now PMP PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method