After establishing a cost baseline and the appropriate cost management plan for a complex hybrid...

After establishing a cost baseline and the appropriate cost management plan for a complex hybrid project, the project is still being challenged with cases of budgetary variations. What should the project manager do?

A.

Track budget variations and work with the key stakeholders to adjust as necessary.

B.

Approve budget variations upon request only when the cost performance index (CPI) is above 1.

C.

Reject budget variations upon request to discourage the waste of money on the project.

D.

Approve budget variations upon request to encourage rapid delivery of some components.

PMI PMP Summary

  • Vendor: PMI
  • Product: PMP
  • Update on: Dec 5, 2025
  • Questions: 2040
Price: $52.5  $149.99
Buy Now PMP PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method