An agile project team is building a new product.

An agile project team is building a new product. The stakeholders require ongoing

illustration of project business value.

How should the project manager proceed?

A.

Prepare performance value reports for the business on an ongoing basis.

B.

Include demonstrations of the built portion of the product at the end of every sprint.

C.

Prepare a project report for the stakeholders and distribute it weekly.

D.

Confirm the minimum viable product (MVP) and demonstrate it to the business when it is ready.

PMI PMP Summary

  • Vendor: PMI
  • Product: PMP
  • Update on: Aug 13, 2025
  • Questions: 1988
Price: $52.5  $149.99
Buy Now PMP PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method