An agile project team is working on an infrastructure product to be delivered incrementally over...

An agile project team is working on an infrastructure product to be delivered incrementally over several iterations. Midway through the third iteration, the whole company is

informed that the operating systems supported by the infrastructure will be terminated in the upcoming quarter. Several thousand machines will be impacted by this change.

What should the project manager do first?

A.

Prioritize the upgrade of project machines with the IT department.

B.

Inform the product owner and request more project resources.

C.

Schedule a session with stakeholders to understand the impact.

D.

Add product backlog items to prioritize operating system stories.

PMI PMP Summary

  • Vendor: PMI
  • Product: PMP
  • Update on: Aug 13, 2025
  • Questions: 1988
Price: $52.5  $149.99
Buy Now PMP PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method