An important national project is in (he execution phase.

An important national project is in (he execution phase. A time constraint activity must be conducted on-site by a specialist from another country. Due to travel restrictions, the specialist cannot perform the activity on-site. The activity cannot be completed without the specialist's expertise. The project team is actively seeking assistance in order to complete the job on time.

What should the project manager do to help the project team?

A.

Reschedule the project until the local travel restrictions are lifted.

B.

Schedule virtual sessions with the specialist to guide the team in completing the activity.

C.

Seek additional budget to train the project team on the required skill set.

D.

Refer to the organization's lessons learned repository and find an alternative solution.

PMI PMP Summary

  • Vendor: PMI
  • Product: PMP
  • Update on: Aug 13, 2025
  • Questions: 1988
Price: $52.5  $149.99
Buy Now PMP PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method