An organization is undergoing an agile transformation.

An organization is undergoing an agile transformation. The executive leadership team is concerned that they will lose control over the scope of the project.

What should the project manager, who is responsible for this project, do to mitigate this risk?

A.

Ensure that the executive leadership team approves all scope that is being proposed by the multiple agile teams to avoid misalignment.

B.

Propose a governance model that empowers the teams while providing the necessary oversight to the executive leadership team.

C.

Propose a multilayered gate system based on risks and financial expenditures, involving the executive leadership team as needed.

D.

Assure the executive leadership team that the current governance model will not be affected by the agile approach.

PMI PMP Summary

  • Vendor: PMI
  • Product: PMP
  • Update on: Aug 13, 2025
  • Questions: 1988
Price: $52.5  $149.99
Buy Now PMP PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method