Developers spend most of the sprint writing code for user stories, leaving little time for...

Developers spend most of the sprint writing code for user stories, leaving little time for testing. As a result, user stories cannot be tested in time and the stories remain unfinished by the end of the iteration, resulting in poor metrics.

What should the scrum master do first in this situation?

A.

Divide the user stories into two categories: development stories and test stories.

B.

Increase the number of developers on the team so stories are completed faster.

C.

Revalidate the team's velocity to ensure development and testing can be completed within the iteration.

D.

Request the developers work overtime to ensure the testers have enough time to perform their tests.

PMI PMP Summary

  • Vendor: PMI
  • Product: PMP
  • Update on: Aug 13, 2025
  • Questions: 1988
Price: $52.5  $149.99
Buy Now PMP PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method