During a project’s third iteration, two of the existing team members were replaced As the...

During a project’s third iteration, two of the existing team members were replaced As the project entered the next iteration, the team velocity dropped and the performance started to slip.

What should the project manager do?

A.

Guide the team to revert back to the forming and storming stages

B.

Escalate the issue to the project sponsor.

C.

Convene a team building event to address key performance indicators (KPIs).

D.

Discuss the decrease in productivity with human resources

PMI PMP Summary

  • Vendor: PMI
  • Product: PMP
  • Update on: Aug 13, 2025
  • Questions: 1988
Price: $52.5  $149.99
Buy Now PMP PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method