During a retrospective review, many project team members say they are not completing tasks during...

During a retrospective review, many project team members say they are not completing tasks during the iterations because of interruptions and requests for help from other teams. As a team facilitator, what should the project manager do to avoid this?

A.

Identify the problem's root causes and define the ground rules with all project team members to minimize interferences.

B.

Recommend to the project team members that they should improve their planning and make their stories smaller.

C.

Reunite with the project team members affected and tell them not to reduce the team's capacity.

D.

Hire a coach to help all project teams to improve their abilities to solve problems on their own.

PMI PMP Summary

  • Vendor: PMI
  • Product: PMP
  • Update on: Aug 13, 2025
  • Questions: 1988
Price: $52.5  $149.99
Buy Now PMP PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method