PMI PMP Question Answer
During the implementation phase of a construction project the customer asked a key subcontractor to deliver a work package ahead of time The subcontractor was not prepared for it and asked the project manager for additional budget What should the project manager do first?
PMI PMP Summary
- Vendor: PMI
- Product: PMP
- Update on: Aug 13, 2025
- Questions: 1988