During the third iteration of a project, the product owner requests another mandatory feature.

During the third iteration of a project, the product owner requests another mandatory feature. This also happened in the previous two sprints, which resulted in failure and caused frustration within the team.

What should the project manager do next?

A.

Incorporate the changes in the last sprint before the first release.

B.

Call for an internal meeting to discuss the changes and their value.

C.

Ask the product owner to prioritize the backlog with the project team.

D.

Request the scrum team to prioritize the product backlog.

PMI PMP Summary

  • Vendor: PMI
  • Product: PMP
  • Update on: Aug 13, 2025
  • Questions: 1988
Price: $52.5  $149.99
Buy Now PMP PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method