From previous lessons learned working with a client, a project manager notes that the client's...

From previous lessons learned working with a client, a project manager notes that the client's turn-around times on documents sent for approval were very slow and well outside of the agreed timelines At the initial kick-off meeting with the same client, how should the project manager approach this issue for the new project?

A.

Inform the client that extra resources will be added to give the client more time for reviews.

B.

Update the project risk register with the potential for delays

C.

• Work with the client on an acceptable amount of time for document approval

D.

Inform the client of their responsibility in relation to document approval

PMI PMP Summary

  • Vendor: PMI
  • Product: PMP
  • Update on: Aug 13, 2025
  • Questions: 1988
Price: $52.5  $149.99
Buy Now PMP PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method