PMI PMP Question Answer
In a fixed-budget project, the team has received a prioritized list of requirements and has nearly completed the first iteration. The CEO has decided to redirect the team to focus on creating a presentation for their upcoming technology summit. The CEO is not flexible about this request.
Which two actions should the project manager take? (Choose 2)
PMI PMP Summary
- Vendor: PMI
- Product: PMP
- Update on: Oct 19, 2025
- Questions: 594