In a project meeting, the development team reported a delay in a critical activity.

In a project meeting, the development team reported a delay in a critical activity. The root cause of the delay was traced to a missing response from the legal department.

What should the project manager do?

A.

Review the processes for reporting issues and the escalation paths with the project team.

B.

Schedule a session with the legal and development teams to resolve the issue.

C.

Work with the legal team and the project sponsor to resolve the issue immediately.

D.

Escalate the issue to the project sponsor to get support for the development team.

PMI PMP Summary

  • Vendor: PMI
  • Product: PMP
  • Update on: Aug 2, 2026
  • Questions: 187
Price: $52.5  $149.99
Buy Now PMP PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method