PMI PMP Question Answer
In an advanced stage of a project a stakeholder who is not receiving the project status report communicates this to the project manager After checking, the project manager determines that the person is registered as a stakeholder but was not included in the communications management plan.
What should the project manager do next1?
PMI PMP Summary
- Vendor: PMI
- Product: PMP
- Update on: Aug 13, 2025
- Questions: 1988