In an iteration-based marketing project, a product is scheduled to be launched at the sixth...

In an iteration-based marketing project, a product is scheduled to be launched at the sixth iteration In the third iteration demo the marketing team expressed that they need five iterations to launch the product and they have not started yet

What should the project team have done to avoid this issue?

A.

Held a touchpoint with marketing before the demo to discuss any impediments

B.

Scheduled a demo presentation of the product during the first reason

C.

Asked the marketing team to start working on the product immediately

D.

Confirmed marketing requirements and constraints when adding to the backlog

PMI PMP Summary

  • Vendor: PMI
  • Product: PMP
  • Update on: Aug 13, 2025
  • Questions: 1988
Price: $52.5  $149.99
Buy Now PMP PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method