Near the closing stage, a project is delayed due to staff shortages.

Near the closing stage, a project is delayed due to staff shortages. In order to meet the mandatory deadline, additional resources are necessary, but there is no additional budget. What should the project manager do first to obtain the funding to hire the needed resources?

A.

Ask the sponsor for additional financial resources

B.

Introduce a change request

C.

Use management reserves

D.

Update baselines to accommodate the delay

PMI PMP Summary

  • Vendor: PMI
  • Product: PMP
  • Update on: Mar 19, 2026
  • Questions: 2134
Price: $52.5  $149.99
Buy Now PMP PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method