The change control board (CCB) rejects a change request submitted by a subject matter expert...

The change control board (CCB) rejects a change request submitted by a subject matter expert (SME) The SME refuses to accept this rejection and does not want to continue the project without the change

What should the project manager have done to avoid this situation?

A.

Requested that the sponsor approved the change request first.

B.

Assessed the change's overall impact to the project before submission

C.

Ensured that the change request was aligned with the project scope

D.

Submitted the change request directly to the CCB

PMI PMP Summary

  • Vendor: PMI
  • Product: PMP
  • Update on: Aug 13, 2025
  • Questions: 1988
Price: $52.5  $149.99
Buy Now PMP PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method