The main project stakeholder was fired and replaced by another stakeholder.

The main project stakeholder was fired and replaced by another stakeholder. The

new stakeholder reviewed the project scope and requested numerous changes, arguing that

the stakeholder's team is unhappy with the results to date.

What should the project manager do?

A.

Put the new requirements in the backlog with high priority and implement the

requested changes.

B.

Put the new requirements in the backlog and submit a formal change request for

approval.

C.

Put the new requirements in the backlog and let the product owner check their value

and priority.

D.

Put the new requirements in the backlog with low priority and implement the requested

changes.

PMI PMP Summary

  • Vendor: PMI
  • Product: PMP
  • Update on: Aug 13, 2025
  • Questions: 1988
Price: $52.5  $149.99
Buy Now PMP PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method