The project team is planning a schedule with limited information.

The project team is planning a schedule with limited information. The team |s having

issues identifying the detailed tasks and estimating task durations.

Which three techniques should the project manager use? (Choose three)

A.

Rolling wave planning and an adaptive approach

B.

Relative estimation to determine the task or deliverable sizes

C.

Iterations and reviews to continuously keep adapting the plan

D.

Bottom-up estimating based on a work breakdown structure (WBS)

E.

Gantt chart that includes milestones and deadlines https://www.projectmanager.com/blog/project-management/planning-techniques-for-projects

PMI PMP Summary

  • Vendor: PMI
  • Product: PMP
  • Update on: Jul 29, 2025
  • Questions: 1877
Price: $52.5  $149.99
Buy Now PMP PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method