The project team members have finalized the technical specifications after their discussion with the machine...

The project team members have finalized the technical specifications after their discussion with the machine manufacturers. However, it has been identified that the specifications are not aligned with the project management office (PMO). The project team members are confident about their choice of specifications.

What should the project manager do in this situation?

A.

Request a decision from the project sponsor.

B.

Give approval of the technical specifications.

C.

Ask the sponsor for additional funding to hire a senior subject matter expert (SME).

D.

Schedule a meeting with all of the subject matter experts (SMEs) to discuss.

PMI PMP Summary

  • Vendor: PMI
  • Product: PMP
  • Update on: Aug 13, 2025
  • Questions: 1988
Price: $52.5  $149.99
Buy Now PMP PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method