The sponsor approaches the project manager with new features they want added tothe project.

The sponsor approaches the project manager with new features they want added to

the project. The project is 95% complete, but the sponsor insists that continued support for the

project relies on the addition of the new features.

What should the project manager do?

A.

Assess the impact of the features and refer it to the change control board (CCB).

B.

Implement the new features after assessing the impact.

C.

Reject the new features since it amounts to gold plating.

D.

Add the new features to avoid losing the sponsor's support for the project.

PMI PMP Summary

  • Vendor: PMI
  • Product: PMP
  • Update on: Aug 13, 2025
  • Questions: 1988
Price: $52.5  $149.99
Buy Now PMP PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method