The start of a 12-month project has been delayed by 2 months The project has...

The start of a 12-month project has been delayed by 2 months The project has a fixed budget, deadline and product specifications. What should the project manager do next?

A.

Schedule a time to negotiate a trade-off regarding the quality of the product with the customer

B.

Meet with the risk manager to identify potential threats related to the schedule delay.

C.

Set up a meeting with the project sponsor and submit a change request to the scope of the product

D.

Start the project plan for the scope and quality and identify options to deliver and meet stakeholders expectations

PMI PMP Summary

  • Vendor: PMI
  • Product: PMP
  • Update on: Aug 13, 2025
  • Questions: 1988
Price: $52.5  $149.99
Buy Now PMP PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method