PMI PMP Question Answer
Two weeks after the approval of the project management plan for a global project, the project manager noticed that it was approved based on a different level of understanding by international stakeholders and is not what the project manager presented for approval What should the project manager have done to prevent this from happening?
PMI PMP Summary
- Vendor: PMI
- Product: PMP
- Update on: Aug 13, 2025
- Questions: 1988