Special Halloween Sale - 75% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: vce75

While preparing an earned value analysis (EVA) for the sponsor, the project manager provided this...

While preparing an earned value analysis (EVA) for the sponsor, the project manager provided this information in the latest project report:

    Approved Work Package Cost Estimates: US$9,500

    Contingency reserves: $500 %

    Management reserves: 10% of contingency reserves

    Percent complete of the project: 50%

    Planned percent of the project: 40%

    Actual costs of the project: US$4,500

What is accurate about the project status?

A.

The actual work is 25% more than the planned work.

B.

The project cost is 10% lower than planned.

C.

The actual work is 25% less than the planned work.

D.

The project cost is 10% higher than planned.

PMI PMP Summary

  • Vendor: PMI
  • Product: PMP
  • Update on: Nov 2, 2026
  • Questions: 187
Price: $52.5  $149.99
Buy Now PMP PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method