While reviewing a project with high-level executives, the project manager realizes that the conversation always...

While reviewing a project with high-level executives, the project manager realizes that the conversation always deviates to other topics instead of the project itself.

What two actions should the project manager take? (Choose 2)

A.

Review with the team all of the topics that came up during the meeting.

B.

Extend the meeting time to review additional topics.

C.

Redirect the conversation to the project updates.

D.

Restrict offline reviews to critical points related to the project.

E.

Schedule effective communications training for the stakeholders.

PMI PMP Summary

  • Vendor: PMI
  • Product: PMP
  • Update on: Oct 19, 2025
  • Questions: 594
Price: $52.5  $149.99
Buy Now PMP PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method