At the stage 2 boundary, the project manager recommends adding the replacement subcontractor’s account manager...

At the stage 2 boundary, the project manager recommends adding the replacement subcontractor’s account manager to the project board to represent supplier interests during stage 3.

Which practice is being applied in ‘managing a stage boundary’?

A.

Plans

B.

Organization

C.

Quality

D.

Progress