Identify the missing words in the following sentence.

Identify the missing words in the following sentence.

The 'directing a project' process starts when [ ? ] and is triggered by the request to initiate a project.

A.

the 'starting up a project' process is completed

B.

the project mandate has been approved by the project board

C.

the project board has agreed the project strategies

D.

corporate, programme management or the customer have authorized a project

PRINCE2 Prince2-Foundation Summary

  • Vendor: PRINCE2
  • Product: Prince2-Foundation
  • Update on: Jul 25, 2025
  • Questions: 461
Price: $52.5  $149.99
Buy Now Prince2-Foundation PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method